The End is in Sight

Remember how far you’ve come, not just how far you have to go.

– Rick Warren

WEEK TEN
It seems like there is so much to be done prior to our pre-settlement walkthrough that’s just over two weeks away, but knowing how much can be accomplished each week, we’re excited to see it all come together.

This week, LVP was finished, drywall patching and sanding continued, the first coat of paint was added to walls doors and trim, the shower tile and door were installed, doorknobs were added, shelving was added in pantry, closets and laundry, electrical finishing began, HVAC and electricians installed fans and AC, and kitchen countertops and sink were installed.

There are some things that need to be repaired or redone, but overall, things are moving along well. The replacement for the damaged cabinet hasn’t arrived yet, the stone along the sloped yard was laid at an angle instead of straight and will be removed and reset, there are issues with the downspouts and drains that need to be addressed and a broken window needs to be replaced. Joey is on top of it, so we aren’t worried, but anxious to see what the next two weeks bring.

Kitchen with granite counters and electrical outlets
Even the kitchen sink!
Painted walls and one of the nicest electricians in the world
Painted doors with handles in master bath
Shower tile and door installed
AC unit set and operating

An Inside Job

Mirror, mirror on the wall.

WEEK NINE
The inside of the house had major transformation this week. At the beginning of the week, the walls were primed and the ceilings were textured. We were shocked when we returned toward the end of the week to see everything else that was completed. All interior doors were hung and our cottage front door was swapped in. The coffered ceiling, baseboards, windowsills and door trim were added, kitchen and bathroom cabinets were set (except one that was damaged in shipping), bathroom vanities were put in and the mirrors have been hung, tile floors in both baths and laundry were completed, plus the insulation was added in the basement. Then, Friday, the flooring was put down in the great room and kitchen.

With our walkthrough date of July 15 approaching, we’ve started packing and planning the move. Plus, this week we were able to get the measurements to order our bedroom window treatments so we’ll have them when we move in. It’s hard to believe we’ll be moving in four short weeks!

Coffered ceiling trim
Textured ceiling completed
Master bath tile floor
Kitchen cabinets set
Master bath cabinets, countertops and windows
Windowsills and baseboards
Great room flooring installed

Stones and Mud

Even a brick wants to be something.

– Louis Kahn

WEEK EIGHT
Work continued on both the interior and exterior this week. We were surprised to see the stone was set over the weekend. What a beautiful sight seeing all of the colors we selected come to life together!

Also this week, the drywall mud was added and sanding began. The fireplace surround was added and the gutters and downspouts were installed. Plus, a whole bunch of “goodies” arrived in the garage.

Joey took some time off, but still took the time to call this week with an update. Next up, wall primer, floors and trim.

Stone added to exterior
Sierra PA Ledgestone
Fireplace Surround – Absolute black granite
Gutters and downspouts installed
Arches and drywall mud
Drywall mud and sanding on master walls and ceilings
Garage full of cabinets, doors, trim and other supplies

Puttin’ Up Walls

Another brick in the wall.

-Roger Waters

WEEK SEVEN

It’s hard to believe we’re more than halfway through our build with the completion of week seven. Big changes occurred on both the interior and the exterior this week. The siding and shutters were completed on the exterior and the stone was delivered. We also saw what is probably the biggest change to date inside; the drywall was hung and each room took shape.

We’ve also started our shopping for appliances that are not included and some new furniture for rooms where we’ve decided to update. I’ve been pleasantly surprised at how willing retailers have been to hold the purchases for weeks before delivering to our new address.
Next week, the drywall will be taped and finished and the stone will be added to the exterior.

We are excited to see more progress and remain grateful for all the great folks working on our home, from the tradesmen, the PMs and sales reps to our real estate agent for our current home and we cannot forget our amazing banker. We cannot thank you all enough!

Siding almost completed – Photo credit to our sales rep Jenn Kingure
Siding and shutters completed
Siding completed back of house
Stone is here!
Drywall hung – looking through great room to morning room
Drywall in master with tray ceiling
Drywall in master bath

It’s a Date!

A dream written down with a date becomes a goal. A goal broken down into steps becomes a plan. A plan backed by action makes your dreams come true.

Greg Reid

WEEK SIX

What a week! More electric work was completed including the installation of the panel. Siding was started, no easy task with the angles along the sloped yard. More dirt arrived and additional grading was done in the back of the house. Insulation was installed and inspected. The crew did a really great job on the insulation. Not only was insulation added to the exterior walls, but all gaps along windows, doors and between boards were filled with foam. Even the holes in electrical and fixture boxes in the ceiling were sprayed with foam plus caulk was added to ensure the drywall seals tightly to ensure energy efficiency. And last this week, drywall was delivered.

There was lots of progress, but our biggest news is that we met with Joey for our pre-drywall walkthrough. Everything is looking great. We didn’t have any concerns at walkthrough, just a few wishes and questions. Joey also gave us our date for final walkthrough – July 15th, 2019! While that is unbelievably exciting, it is also just a little bit terrifying thinking about everything that needs to happen in the next six weeks. Between the sale of our current home, packing, moving plans, financing and seeing the rest of the house completed, it will be a very busy time.

Although it can feel busy and stressful, we are truly blessed to be living this experience. I can’t say enough about all the great people working on our home.

Siding started on north side
Siding corners, ledges and trim
Electric panel
Grading behind house
Insulation, caulk at drywall and foam on wiring

Insulated wall and delivered drywall