Timeline

Click on the date to see details and pictures from each step.

December 13, 2018 – Signed purchase agreement for new home

December 19, 2018 – Meet with NVR to review financing options

December 23, 2018 – Structural change order deadline

January 2, 2019 – Meet with Guardian for security and technology

January 5, 2019 – Color and finish selection meeting

January 13, 2019 – Flooring, wiring and non-structural change order deadline

April 15, 2019 – Pre-construction meeting

April 24, 2019 – Dig foundation

April 25, 2019 – Set footer forms

April 26, 2019 – Pour footers

April 30, 2019 – Set wall forms

May 1, 2019 – Pour concrete walls

May 2, 2019 – Remove forms

May 3, 2019 – Waterproofing and drains

May 6, 2019 – Backfill and grading

May 7, 2019 – Set beams and frame garage

May 8, 2019 – Floor joists and floor sheeting

May 9, 2019 – Wall framing, doors and windows

May 10, 2019 – Roof trusses and start roof sheeting

May 13-14, 2019 – Roof shingled

May 14-16, 2019 – Rough plumbing completed Tuesday and Wednesday, inspected Thursday

May 17, 2019 – concrete floors basement, garage and front porch

May 20, 2019 – Garage doors and walk out door installed

May 20-21, 2019 – HVAC rough

May 22, 2019 – Cable, phone and network wiring

May 22-24, 2019 – Rough and underground electric

May 27-29, 2019 – Insulation

May 31-June 4, 2019 – Siding and shutters

June 4-6, 2019 – Drywall hung

June 8-10, 2019 – Exterior stone added

June 10, 2019 – Fireplace surround

June 10-?, 2019 – Drywall mud and sanding

June 14, 2019 – Gutters and downspouts

June 17, 2109 – Interior doors hung and cottage front door swapped in

June 18, 2019 – Tile floors

June 19, 2019 – Coffered ceiling, baseboards, windowsills and door trim added

June 19, 2019 – Kitchen cabinets and bathroom vanities set

June 19, 2019Basement insulation

June 20-21, 2019 – LVP flooring

June 24-26, 2019 – Wall, doors and trim painted

June 25, 2019 – Shower tile and door installed

June 27, 2019 – Shelving added in pantry, closets and laundry

June 28, 2019 – Fans and AC functioning

June 28, 2019 – Kitchen countertops and sink installed

July 2, 2019 – Electric finished

July 3, 2019 – Plumbing finished, fireplace finished and tested

July 5, 2019 – Carpet installed, appliances delivered and installed

July 9, 2019 – House cleaned / Final grading

July 15, 2019 – Third party inspection and final walkthrough

July 23, 2019 – It’s ours!!